Construction tender of Vlora By-Pass and Fier By-Pass
Lot 1 Construction of Vlora Bypass
Vlora bypass consists of a 29 km long route composed of a new single carriageway highway, numerous new bridges and 8 at grade junctions. The project starts from the Roundabout at the end of the Double Carriageway Levan Vlora.
Status of the Project: The commencement date was set at 15.04.2015 for a construction duration of 30 months, i.e. completion at 14.10.2017. The construction did not progress as scheduled as the mobilization of the Works Contractor was not as expected due mostly to its own internal problems. After 24 months within the duration of the project, approximately 12% was implemented. Consequently, there was a termination by the Employer (Albanian Road Authority) on 20.04.2017
The Albanian Road Authority intends to proceed to tender the remainder of the works for the project at hand, taking into account the current status of the project, the remaining works to be executed, the approved designs of the project and other issues which were created within this period.
Earthworks
Excavation in soft or intermediate soils 508 000 m3
Excavation in rock 1 000 000 m3
Embankment formation 5000 000 m3
Road Pavement
Sub-base layer 175 000 m3
Bituminous base course 353 000 m2
Binder course 353 000 m2
Bituminous wearing course 353 000 m2
Construction Period is 27 months.
Lot 2 Construction of Fieri Bypass
The project of the construction of the Fier - Levan road substantially is the construction of the by-pass of Fier. This project is part of the construction of the north south corridor that crosses all the Country from the Montenegro border to the Greek border the road length is about 22 Km highway type.
The road starts around 60Km south of the port of Durres at the small town of Mbrostar, bypasses the town of Fier on the west side at few kilometres from the sea side and ends at the main roundabout at south of the small city of Levan. The road platform width is 22m and includes: 2 lanes for each directions of 3.75m size; central reserve 3.5m.
The Project has been started by another Contractor but the Employer has decided to terminate the original Contract and at moment around 55% of the works is performed. there was a termination by the Employer (Albanian Road Authority) on 20.04.2017.
The Albanian Road Authority intends to proceed to tender the remainder of the works for the project at hand, taking into account the current status of the project, the remaining works to be executed, the approved designs of the project and other issues which were created within this period.
The remaining work to complete are mainly: completion of some concrete structures and repair works on concrete structures, completion of bridge concrete basement and erection of metallic structures on the bridge as well construction of precast elements between the beams and concrete deck slabs on bridges, completion of various small drainage structures, overpasses and underpasses, completion of embankment formation, backfilling of structures, reinforcing earth, lime/cement treatments (stabilization), landscaping, top
soiling and construction of cut off diches, subbase, crushed stone base, asphalt works, guard rail, traffic signs and withe
Construction Period is 15 months.
Prequalification and tendering for contracts to be financed with the proceeds of a loan from the Bank is open to firms and joint ventures of firms from any country.
Prequalification documents may be obtained from the office at the address below upon payment of a non-refundable fee of Euro 100.00 (one hundred) or equivalent in a convertible currency.
Payment to obtain the Tender Documents can be made by bank transfer
If requested, the documents can be dispatched electronically in PDF format free of charge. The prequalification documents must be duly completed and delivered to the address below, on or before 25th October 2017. Documents which are received late may be rejected and returned unopened.